White Water World - Dreamworld [2006 - Watpac]

Job: White Water World (Dreamworld)
Client: Watpac
Tonnage: 200t
Date Commenced: August 2006
Duration Of Scope: 3 Months
Specification:

Welding AS1554.1SP
Fabrication AS4100
Protective Coating: Hot Dip Galvanized, Blasted & Painting, 2 coat system 200 microns.


Description :

Dreamworld one of Australia’s biggest and best theme parks created a water park next door, Watpac contracted Alltype Welding to do all Fabrication, installation and erection of structural steel, stairways, towers, decks, cone frame for a large ride with a radius of 20mtrs and fiberglass slides. Our equipment came in handy with the reach and lift of the 50t liebherr along with all our boom, scissor lifts and the telehandler to help complete this project in record time.