Job: Powerlink Warehouse, Narangba
Client: McNab Relationship Builders
Tonnage: 268t
Date Commenced: September 2010
Duration Of Scope: Incomplete
Specification:

Welding: AS1554.1 GP
Fabrication: AS4100
Protective Coating: Sandblast (class 2.5) Paint System: Primer - International Paints Intercure 200Hr at 100 Microns, Top Coat - Internation Paints Interthane 990 at 75 Microns.


Description :

Fabrication started in early September on Powerlinks new warehouse in narangba.
With a full crew on deck, Alltype Welding has completed enough of the fabrication to start site works two weeks after fabrication started.
With our 70t Crawler Crane onsite along with 20t Kato rough terrain crane this erection process should be completed in a timely manner.
elevated work platforms of different types makes and models are being used on this site to assist with the structural steel erection process.
This project took longer than expected, due to erecting it over brisbanes big wet of January 2011, now with the project complete,
McNab and the client happy it was erected as quickly as mother nature allowed us to.